MILLEDGEVILLE — A bridge installed Thursday over Tanyard Creek at the Oconee River Greenway allows contractors access to complete Phase 2 expansion.

Heavy rains in the spring and summer delayed contractors.

Weather permitting the project should be complete within two months.

The 33-ton capacity 70-by-10 bridge was pre-ordered. Big R Bridge Company located in Greeley, Colo. delivered the structure to the site for the contractor to assemble and erect. 

Purcell Construction owner Chet Purcell said assembly of the $75,000 bridge took one day.

Oconee River Greenway Authority Executive Director Dr. Heather Langston said Phillips Brothers Contracting, Inc. continues successful and speedy work on the property’s north end. Langston praised Phillips Brothers use of local subcontractors for Phase 2.

One mile of 10-foot concrete trails north of the bridge, a boardwalk over Phase 1 wetlands, overlooks and a more permanent concert stage make up the master plan. 

Creation of a 1.1-acre off-lease dog park highlights Phase 2 also. The park will be handicap accessible featuring water fountains, dog stations and picnic tables.

A large and welcome portion of the Greenway work is the Greene Street extension project. The extended driveway is finished and will become the new, safer entrance.

The concrete drive comes with extra parking also.

Langston said the current entrance will close to all but non-vehicular traffic. Directional signs off Hancock and Elbert streets will help visitors acclimate to entering down Greene.

Total construction costs hover around $1.3 million. The Greenway received a grant and $150,000 in 1-cent sales tax funds together with Bicycling Club of Milledgeville and Greenway foundation contributions to make the projects happen.

The Oconee River Greenway Authority (ORGA) aspires to connect green spaces from north to south creating a natural corridor that improves river access, increases recreational and educational activity and boosts economic potential. Recent Greenway Phase 2 construction and acquisition of the 250-acre Selma Irwin Nature Trail link these goals.

Text Only
Local News
Poll
AP Video
Facebook
Twitter Updates
Follow us on twitter
Parade
Magazine

Click HERE to read all your Parade favorites including Hollywood Wire, Celebrity interviews and photo galleries, Food recipes and cooking tips, Games and lots more.
Stocks
NDN Video